Within the framework of revamping of Wheels Final Inspection Line-2 SME Tomsk Electronic Company being a General Contractor provided the following services:
- Technical requirements generation for process units of the line
- Process plan development including construction task preparation
- Designing PCS, data communications networks, video control systems and dispatch systems
- Selection and process units supply in accordance with the technical requirements worked out and approved by the Customer
- Development of construction documentation and manufacture of equipment for conveyor system
- Development of the equipment for the existing conveying line and data connection with the existing PCS
- Installation supervision and commissioning
|
Implementation of this project enabled:
- Revamping the line non-stop
- Introducing the unified information space of the line and integrating it into the shop space, forming a full electronic certificate of the wheel, recording all parameters and properties of the wheel (paint quality, roto-blast hardening, internal structure etc.) and monitoring the travel of the wheel along the conveying system
- Increasing production of railroad wheels with the increased wear characteristics
|
Final Inspection Line data
Annual capacity, wheels per year
|
330000
|
Annual running time,hours
|
6855
|
Line cycle, sec per piece
|
75
|
Line capacity
|
|
Conveying equipment weight, t
|
60
|
Conveying equipment capacity, kW
|
120
|
External wheel diameter, mm
|
920...1070
|
Wheel mass, kg
|
360...620
|
|